Project Drone Footage: August 2020

The video is available in Spanish here/Este video está disponible en Español aquí

0:03 – Ann Richards School
1:15 – Bear Creek Elementary School
2:26 – New Blazier Relief School3:41 – Bowie High School
4:48 – Doss Elementary School
6:06 – Eastside Memorial Early College High School & International High School at the Original L.C. Anderson Campus
7:23 – Hill Elementary School
8:22 – Murchison Middle School
9:38 – Norman-Sims Elementary School
10:42 – Sánchez Elementary School

Ann Richards School for Young Women Leaders – Filmed 8/20/20 – The Ann Richards project has received permanent power and interior wall and glass installations are ongoing throughout the building. The project is expected to be completed in January 2021.

Bear Creek Elementary School – Filmed 8/20/20 – Bear Creek Elementary School is receiving final interior finishes and undergoing construction clean up. The campus will be ready for students when face-to-face instruction resumes.

Blazier 4-6 School – Filmed 8/20/20 – The Blazier 4-6 School is receiving final interior finishes and undergoing construction clean up. The campus will be ready for students when face-to-face instruction resumes.

Bowie High School – Filmed 8/20/20 – The new Bowie High School Slaughter Lane entry has now been completed and the new Bowie Parking Garage is undergoing final landscaping and construction clean up. The new Bowie Parking Garage will be available to permitted students when face-to-face instruction resumes.

Doss Elementary School – Filmed 8/14/20 – Furniture installations, exterior landscaping, and a flagpole installation is underway at the Doss Elementary Schoolproject site. The project is near completion and will be available for students when face-to-face instruction resumes.

Eastside Memorial Early College High School & International High School at Original L.C. Anderson – Filmed 8/20/20 – Exterior roofing, framing, and waterproofing are ongoing at the Eastside Memorial project site. The project is expected to be completed by July 2021.

Hill Elementary School –  Filmed 8/20/20 –  Perimeter foundation work and elevator pit reinforcement is underway at the Hill Elementary School project site. The project is expected to be completed by August 2021.

Murchison Elementary School –  Filmed 8/20/20 – Furniture installations and exterior finishes are underway at Murchison Elementary School. Final roofing between the new addition and the existing building is ongoing. The project is expected to be completed in early 2021.

Norman-Sims Elementary School – Filmed 8/20/20 – Exterior asphalt paving and interior framing is ongoing at the Norman-Sims project site. The project is expected to be completed in spring 2021.

Sanchez Elementary School – Filmed 8/20/20 – Exterior concrete pours and demolition continue at the Sanchez Elementary School project site. Additionally, interior finishes and framing are ongoing throughout the facility. The project is expected to be completed in summer 2021.