Project Drone Footage: February 2020

The video is available in Spanish here/Este video está disponible en Español aquí

0:03 – New Blazier Relief School
1:07 – Bowie High School
2:09 – Doss Elementary School
3:17 – Eastside Memorial Early College High School & International High School at the Original L.C. Anderson Campus
4:26 – Murchison Middle School
5:28 – New Southwest Elementary School
6:33 – Norman Elementary School

New Blazier Relief Elementary School – Filmed 2/28/20 – Exterior walls and roof work is underway in the New Blazier Relief middle school wings. Primary electrical installations are also ongoing. The project is expected to be completed in August 2020.

Bowie High School – Filmed 2/28/20 – The new Bowie Parking Garage is 65% complete and work on the fourth floor is expected to begin this month. The project is expected to be completed in June 2020. 

Doss Elementary School – Filmed 2/25/20 – Exterior walls and roof installations are underway at the Doss Elementary School campus. The project, which will significantly increase the school’s capacity, is expected to be completed in August 2020. 

Eastside Memorial Early College High School & International High School at Original L.C. Anderson – Filmed 2/26/20 – The structural steel for the four story building has been erected at the Eastside Memorial site. The project is expected to be completed in July 2021.

Murchison Middle School – Filmed 2/14/20 – Interior framing and drywall installation is ongoing in the administration area of the Murchison Middle School project. The school is expected to be completed in January 2021.

New Southwest Elementary School – Filmed 2/28/20 – Exterior wall work and concrete placement for the bus loop continues at the New Southwest Elementary School modernization project. This school is expected to be completed in August 2020.

Norman Elementary School – Filmed 2/26/20 – Structural steel work is ongoing at the Norman Elementary School modernization project. The school is expected to be completed in Spring 2021.